If you share a wall with next door, or dig close to their foundations, the Party Wall etc. Act 1996 may apply. It is separate from planning permission and Building Regulations, and it catches people out.
What the Act covers
It applies to work on a shared wall or floor, to building a new wall on or at the boundary, and to excavation near a neighbour's foundations. Typical triggers on a terrace are cutting in steel beams, raising a wall, building a side-return wall on the boundary and digging new foundations next to theirs.
Notice periods
Notice must be in writing. Work to an existing party wall needs two months' notice. Building a new wall at the boundary needs one month, and so does excavation within the distances set by the Act. Your neighbour then has 14 days to reply.
If they do not respond or dispute it
If there is no reply within the time allowed, a dispute is treated as having arisen and surveyors get involved. A single agreed surveyor can act for both sides, or each owner can appoint their own, and the building owner normally pays the reasonable costs.
What it does not do
A party wall award does not give planning permission, and neighbours cannot stop work that the Act allows. What it does is protect both sides, with a record of the walls before work starts.
How we help
We flag the likely notices at the first visit and give you realistic lead times, so your programme starts from the date notices are served rather than the date you would like to begin. We are not surveyors, and we will suggest a party wall surveyor where one is needed.